What must contractors disclose to clients after a contract is executed?

Prepare for the Arizona Registrar of Contractors Exam. Use flashcards and multiple choice questions with hints and explanations. Ace your test with confidence!

After a contract is executed, contractors must disclose all relevant details to clients, including any delays and change orders. This requirement is crucial for maintaining transparency and trust between contractors and clients. Such communication ensures that clients are kept informed about the project's progress and any factors that may impact the timeline or budget.

Delays can arise due to various unforeseen circumstances, and change orders often reflect necessary adjustments to the work initially agreed upon. By keeping clients updated with this information, contractors help them understand the implications of these changes, which can affect overall satisfaction and the success of the project.

In contrast, disclosing only the project's total cost, the project start date, or opting not to share any details would not adequately meet the requirements for communication post-contract execution. It is essential for contractors to foster a collaborative relationship with their clients, which hinges on regular updates and full disclosure of all relevant project details.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy