What is the deadline to file a lien after a notice of completion is filed?

Prepare for the Arizona Registrar of Contractors Exam. Use flashcards and multiple choice questions with hints and explanations. Ace your test with confidence!

The correct deadline to file a lien after a notice of completion is indeed 60 days. In Arizona, when a notice of completion has been recorded, the period for filing a lien by contractors, subcontractors, and suppliers is shortened to 60 days. This time frame is crucial as it establishes the limits within which parties must assert their rights to secure payment for work performed or materials supplied.

Understanding this timeline is vital for contractors and other parties involved in construction, as failing to file a lien within this period may lead to losing the right to claim against the property for unpaid work. By adhering to the 60-day deadline, individuals ensure their interests are protected and maintain a legal standing to seek compensation through a lien.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy