The correct deadline to file a lien when no notice of completion has been filed is 120 days. This time frame is important as it provides contractors, subcontractors, and suppliers a specific period to assert their claims for payment.

In Arizona, the lien law establishes that if a notice of completion has not been recorded, the deadline to file a mechanic's lien extends to 120 days after the last labor or materials were provided. This rule allows parties involved in a construction project to protect their right to receive compensation for their work by formally filing a lien against the property if they have not been paid.

Understanding the timeline for filing a lien is crucial for those in the construction industry, as failing to do so within the designated timeframe can result in losing the right to claim the outstanding amounts owed.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy